  • Days 29 and 30

    Problem getting roof tiles and door frame. No disabled door’s door frame available anywhere in the UK – would you believe it!! Plumber and electrician have done their first stages.

  • Day 27 & 28

    Render on walls. Roofing felt and lathes in place. Just waiting for slate tiles to arrive.

  • Day 26 Toilet Extension

    Lots of activity with high-tec carpentry tools and the toilet ceiling joists are now up. Work proceeding at a cracking pace and I am really pleased.

  • Day 25b

    The builders are back. They have been working at a cracking pace. Better put the kettle on. Hope they don’t find out what their wheelbarrow was used for on Saturday!

  • Day 25a

    Builders due back today. Nipped out to the Co-Op and bought both Rothley and Mountsorrel branches out of sugar much to the bemusement of the staff.